The Resourcing page shows the people your bids will need, by quarter or by month, against the people on your bench, and where you need to recruit.
What it is
- Demand comes from the roles each bid needs, which the build writes: the role, how many people, their skills, where they must be, onshore or offshore, and when in the contract they start.
- Won bids count in full. Likely bids count as their headcount times their win probability: a bid's own, or else the default for its stage (submitted three in ten, vendor demo five in ten, won in full, the early stages low).
- Supply is your bench: the people whose own title or skills carry the role's specific words (a Java developer counts for Java developers; a .NET developer does not, though both are developers) and who are free by the end of the period.
- The gap is what is left, in a sentence such as "2026-Q4: 3 SAP functional consultants in the United Arab Emirates starting October, none on the bench." A role's gap is counted once, in the period the role starts (its own start when the bid's roles give one); the periods after show the role as Continuing. The nearest period comes first.
- A bid with roles but no contract start is listed under Not in the forecast yet, never placed on a guessed month.
How to use it
- Open Resourcing.
- Choose By quarter or By month, and a team or All teams.
- Read Where you need people first, then each period's roles.
- Press Download CSV or Download Excel for the same figures.
- On a bid, open the Resourcing tab to see its roles and set its Duration (months) and Win probability. Set its contract start on Overview with Edit.
- Owners and the enterprise admin set the Win probability by stage at the foot of the page.
Good to know
- No price, rate or margin is on this page, so HR sees it as it is.
- HR, executives, the enterprise admin and owners see every team; a team director sees their own.
- Ask Biddie "where do I need to recruit for Q4?" for the same answer in words. A quarter without a year means the next time it comes round, this one included (in November 2026, "Q4" is 2026-Q4 and "Q1" is 2027-Q1); "this quarter", "next quarter", "Q4 2027" and a year on its own work too.
- A start that is only the buyer's estimate is not guaranteed and may change.
Common questions
Why is a bid missing from the forecast?
It has no contract start, no roles yet, or a win probability of nothing (lost, no-bid and archived bids count for nothing).
Read the forecast
See where you need people, by quarter or month, role and location.
- Who can use it
- HR, executives, team directors, the enterprise admin and owners.
- Where it is
- Resourcing: By quarter, By month, the teams
- In
- The web app, and the phone, tablet and desktop app
No clip for this one: Not filmed yet: the Enterprise plan arrived in November 2026.
What it does
See where you need people, by quarter or month, role and location.
Step by step
- Open Resourcing.
- Choose By quarter or By month.
- Choose a team, or All teams (on the web).
- Read Where you need people, then each period.
What you see
- Where you need people: one sentence per gap.
- Each period's roles with Needed, won and likely, on the bench, and To find or Covered.
- Not in the forecast yet: bids with roles but no contract start.
Set a bid's start, duration and probability
Put a bid in the forecast with when it starts, how long it runs and how likely it is.
- Who can use it
- Owners, writers and team directors.
- Where it is
- A bid: Overview, Edit (contract start); Resourcing (duration and win probability)
- In
- The web app only
No clip for this one: Not filmed yet: the Enterprise plan arrived in November 2026.
What it does
Put a bid in the forecast with when it starts, how long it runs and how likely it is.
Step by step
- Open the bid and press Edit on Overview.
- Type the Contract start and tick Only the buyer's estimate if that is all it is, then Save.
- Open the bid's Resourcing tab.
- Type the Duration (months) and, if you want one, the bid's own Win probability, then Save.
What you see
- The roles the bid needs, each with how many people, where and when.
- The bid's start and win probability, and whether the probability is the stage's default.
Download the forecast
The forecast as a CSV or Excel file.
- Who can use it
- Everyone who sees the forecast.
- Where it is
- Resourcing: Download CSV or Download Excel
- In
- The web app only
No clip for this one: Not filmed yet: the Enterprise plan arrived in November 2026.
What it does
The forecast as a CSV or Excel file.
Step by step
- Open Resourcing and choose the period and team.
- Press Download CSV or Download Excel.
What you see
- A file with a row per period, role and location. The Excel file adds a sheet of the gaps and one of the bids with no start.
This page is the same help that sits behind the ? on every page of the app. Something it does not answer? Email hello@biddable.ae.